35adef5808 fix(workorders): persist explicit technician assignment 2026-09-29 17:58:52 -03:00
Alexandre Brandizzi
9bad363930 fix(work-orders): cancelling from the board cancels the pending uplift
The board and slide-over cancel a work order through the lifecycle status
patch, which set Canceled without touching uplifts, so a pending uplift
stayed in the approval queue. A patch to Canceled now withdraws pending
uplifts in the same save, each with its own uplift_cancel audit entry, and
runs under the per-work-order gate uplift create uses.
2026-09-25 18:37:56 -03:00
Arthur Bassi
deeb29b512 fix(work-orders): allow Complete without a linked site
Snapshot whatever Site/Vendor/POC data exists instead of gating completion on Locations.
2026-09-10 17:56:00 -03:00
Arthur Bassi
e0139d4601 feat(work-orders): capture Site/Vendor/POC snapshot on Completed
Freeze effective live values on first Completed transition and project them on GET.